BILL · 2003–04 SESSION

HB 2341: Electricity generation

Enacting the model distributed generation interconnection procedures and net metering provisions.

Summary

  • Modifies provisions relating to net metering by customer-generators.
  • Specifies procedures, time lines, and technical specifications for interconnecting a customer's electrical generation facility of 20 megawatts or less to an electrical distribution system.

From the House Bill Analysis (HB 2341), written by the Legislature's nonpartisan staff. Read the full report ↗

Did not pass Did not pass · died in committee
  1. IntroducedJan 12, 2004
  2. Out of committeestopped here
  3. Passed House
  4. Passed Senate
  5. Governor
  6. Law
Prime sponsor
Jeff Morris (D-40)
Introduced
January 12, 2004 in the House
Last action
January 12, 2004

AN ACT Relating to the model distributed generation interconnection procedures and net metering provisions;

Sponsors

Prime sponsor: Jeff Morris (D-40)

2 co-sponsors (2 Democrats, 0 Republicans)

Votes

No recorded floor votes. This measure never reached a floor vote.

History

  1. First reading, referred to Technology, Telecommunications & Energy.
  2. Prefiled for introduction.

HB 2341 in other sessions

Bill numbers restart every two years, so the same number is a different bill in each session.

Report wrong or missing information on this page