BILL · 2011–12 SESSION
SB 6353: Elec transmission facilities
Concerning the application of chapter 80.50 RCW to the construction, reconstruction, or modification of certain electrical transmission facilities.
Summary
- An applicant may choose EFSEC to site any transmission facility 115kV or greater.
From the Senate Bill Report (Orig.) (SB 6353), written by the Legislature's nonpartisan staff. Read the full report ↗
Did not pass Did not pass · died in committee
- IntroducedJan 19, 2012
- Out of committeestopped here
- Passed Senate
- Passed House
- Governor
- Law
- Prime sponsor
- Kevin Ranker (D-40)
- Introduced
- January 19, 2012 in the Senate
- Last action
- April 11, 2012
- Budget
- Has a fiscal note
AN ACT Relating to the application of chapter 80.50 RCW to the construction, reconstruction, or modification of certain electrical transmission facilities;
Sponsors
Prime sponsor: Kevin Ranker (D-40)
Votes
No recorded floor votes. This measure never reached a floor vote.
History
- By resolution, reintroduced and retained in present status.
- By resolution, reintroduced and retained in present status.
- First reading, referred to Energy, Natural Resources & Marine Waters.
SB 6353 in other sessions
Bill numbers restart every two years, so the same number is a different bill in each session.
- SB 6353 (2025–26) Working conn. child care
- SB 6353 (2019–20) Supreme court fiscal notes
- SB 6353 (2017–18) Automatic voter registration
- SB 6353 (2015–16) School levy lid revs./delay
- SB 6353 (2013–14) Unif. power of attorney act
- SB 6353 (2009–10) Receivership statutes
- SB 6353 (2007–08) Public transportation fares
- SB 6353 (2005–06) Recreational landowners